Postby twincitizen » December 12th, 2016, 4:37 pm

It's still probably too early for an "E Line" topic, but given the announcement in the aBRT general thread, I moved some conversation here.

Something that gives me pause is that reconstruction of Hennepin Avenue is not yet in the Capital Improvements Project plan. That means it is extremely unlikely to take place before 2021 (the furthest out year of the current plan). If you assume the B Line (Lake St) and D Line (Chicago-Fremont) open around 2020-2021, that would put the E Line in 2022 at the earliest. Metro Transit wouldn't want to open an aBRT line on a street that has an impending reconstruction, so you have to assume there will be some attempt to time the two projects.

Has anyone heard anything about getting Hennepin (bottleneck to Lake) reconstruction scheduled for the early 2020s? Recall that earlier this year the City started holding meetings about Hennepin Ave downtown (Washington to 12th St), even though that is scheduled for 2020 construction.

thatchio
Nicollet Mall
Posts: 180
Joined: August 2nd, 2012, 6:49 am

Re: Hennepin Avenue Transit (Uptown to Downtown)

Postby thatchio » December 13th, 2016, 12:03 am

Let's not sell bus improvements short. The A line was a small investment in the grand scheme of things and there is no reason why bus improvements have to come in the form of the full suite of improvements. Cities, counties, and transit agencies could invest strategically to improve key problem spots.

For example, bus shoulders/lanes through key congestion points would be a political investment with modest amounts for signage and paint. Traffic signal priority, depending on how it is executed, at key intersections is not as expensive as you'd think. Doing it along an entire corridor is more expensive and certainly is influenced by existing traffic signal equipment and the type of priority being provided.

What would likely be in the more expensive bucket is specialized bus fleet, major shelter construction, and off-vehicle payment vending. While these items help take bus service to the next level, if resources are constrained (which they are), focus should go toward looking system-wide for the types of improvements that could be afforded.

In Minneapolis, the city could propose creating a program to improve bus operations by investing in traffic signal improvements/detection devices, signage, and paint. As a program, it could target key opportunity spots instead of trying to geographically target the investment to strictly one corridor that really ought to be addressed as a part of a major rebuild of the street.

mattaudio
Stone Arch Bridge
Posts: 7527
Joined: June 19th, 2012, 2:04 pm
Location: NORI: NOrth of RIchfield

Re: Hennepin Avenue Transit (Uptown to Downtown)

Postby mattaudio » December 13th, 2016, 9:50 am

Additionally- I think the city and/or county could take a larger role in improving transit amenities on rebuilt corridors. The projects I've seen involve agencies making assumptions about how buses work, or assuming the status quo, and then Metro Transit jumps in at the end. Could the lead agencies on street rebuilds be a little more active on pushing stop consolidation, far-side stop locations, bus bulb/larger amenity-zone space, etc?

twincitizen
Moderator
Posts: 5928
Joined: May 31st, 2012, 7:27 pm
Location: Standish-Ericsson

Re: Hennepin Avenue Transit (Uptown to Downtown)

Postby twincitizen » April 12th, 2018, 8:28 am

So who went to the open house last night, what did you see, etc? Where are the aBRT stops? How many lanes, any transit priority?

Here's the City's project page: http://www.ci.minneapolis.mn.us/cip/fut ... nepinSouth
Flyer for last night's meeting: http://www.ci.minneapolis.mn.us/www/gro ... 209903.pdf
2023 construction

Tcmetro
Wells Fargo Center
Posts: 1228
Joined: May 31st, 2012, 8:02 pm
Location: Chicago (ex-Minneapolitan)

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby Tcmetro » April 13th, 2018, 4:52 pm

The layout shows three "E Line" stops along Hennepin, at Franklin, 25th, and Uptown TC. The rapid bus study from 2011 recommended 24th and 26th, although I suppose there is plenty of time to change the locations.

Hopefully the E Line can start when the construction wraps up in 2023!

mattaudio
Stone Arch Bridge
Posts: 7527
Joined: June 19th, 2012, 2:04 pm
Location: NORI: NOrth of RIchfield

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby mattaudio » April 13th, 2018, 6:45 pm

They really need to do a full transitway with a few more stops than that, and use it for all local bus routes on Hennepin. Stops at Franklin, 22nd, 25th, 27th, and Uptown TC.

grant1simons2
IDS Center
Posts: 4184
Joined: February 8th, 2014, 11:33 pm
Location: Marcy-Holmes

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby grant1simons2 » April 13th, 2018, 11:55 pm

... and a big old university is forgotten about

EOst
Capella Tower
Posts: 2183
Joined: March 19th, 2014, 8:05 pm
Location: North End, Saint Paul

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby EOst » April 14th, 2018, 12:24 pm

^Pretty mystifying to me that the E Line plans don't involve an extension along the 6U route to Stadium Village.

twincitizen
Moderator
Posts: 5928
Joined: May 31st, 2012, 7:27 pm
Location: Standish-Ericsson

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby twincitizen » April 14th, 2018, 4:28 pm

Let’s try to keep this topic limited to the portion of Hennepin being reconstructed (and the E Line stations that will be built as part of the project).

Was there something at the meeting confirming that the E Line plan was identical to the 2012 ATCS study? Or are y’all just assuming so? The E Line planning effort doesn’t really begin until 2019-2020 so I’d urge caution on assuming anything.

On one hand, Franklin-25th-Uptown is pretty aggressively far apart for what will be the “main” frequent service in this corridor. That’s probably close to how subway/LRT stations would be spaced in this environment.

The downside is that wide station spacing is too far to eliminate local stops entirely. While aBRT isn’t going to have stops exactly every 1/4-mile, an alternate of Franklin - 24th - 26th(or midblock 26th/27th) - Uptown might be a reasonable distance that would still allow elimination of remaining local stops in this stretch

EOst
Capella Tower
Posts: 2183
Joined: March 19th, 2014, 8:05 pm
Location: North End, Saint Paul

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby EOst » April 14th, 2018, 5:33 pm

It doesn't mean a ton, but this map from their rapid bus page (map updated a month ago, according to the filename) still has the E Line terminating downtown:

Image

mamundsen
Foshay Tower
Posts: 970
Joined: November 15th, 2012, 10:01 am

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby mamundsen » April 14th, 2018, 9:36 pm

This map would look a lot more complete with the Riverview, Rush, Gold Line and something along 36 or RT 3 (enhanced).

thatchio
Nicollet Mall
Posts: 180
Joined: August 2nd, 2012, 6:49 am

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby thatchio » April 15th, 2018, 10:05 am

If there were ever a subway, there would likely be only one station in between Loring Park and Uptown Transit Center. Stations are expensive. That said, aBRT is not as capital intensive. Things to consider: how should surface transit operate in this section, especially if there are both local and aBRT routes? aBRT will need to occasionally pass local buses.

I would hope that Hennepin improvements would include at least:
- buses the ability to get in front of the general purpose traffic, such as bus only signals with leading interval timing.
- bus only lanes between Franklin and 25th, at least.
- removal of the bus stops at 28th and 22nd
- no beg buttons
- improved crosswalks that make it much more clear to drivers that they should stop further back and that they shouldn't queue in the intersection
- additional left-turn restrictions
- managed public parking on the side streets for first block between Hennepin and adjacent streets to off-set lost parking along Hennepin

grant1simons2
IDS Center
Posts: 4184
Joined: February 8th, 2014, 11:33 pm
Location: Marcy-Holmes

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby grant1simons2 » April 15th, 2018, 11:14 am

"beg buttons" are required by ADA. Many are hooked up incorrectly and require a push to cross. We just need to be sure they get connected.

User avatar
Anondson
Capella Tower
Posts: 3330
Joined: July 21st, 2013, 8:57 pm
Location: Where West Minneapolis Once Was

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby Anondson » April 15th, 2018, 1:07 pm

You know how car washes have sensors that alert drivers to back up when you pull in too far? Heavily used crosswalks should get this to buzz at drivers who stop on crosswalk paint.

Does the ADA require beg buttons even if the walk light is set to always happen like the vehicle traffic lights always cycle even when no cars are present?

intercomnut
Union Depot
Posts: 398
Joined: April 23rd, 2015, 1:04 pm

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby intercomnut » April 15th, 2018, 1:14 pm

Anondson wrote:
April 15th, 2018, 1:07 pm
You know how car washes have sensors that alert drivers to back up when you pull in too far? Heavily used crosswalks should get this to buzz at drivers who stop on crosswalk paint.

Does the ADA require beg buttons even if the walk light is set to always happen like the vehicle traffic lights always cycle even when no cars are present?
Yes, because the buttons contain audible and tactile (the button vibrates) cues to tell people who cannot see and/or hear when to cross.

Silophant
Moderator
Posts: 3374
Joined: June 20th, 2012, 4:33 pm
Location: The Gateway

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby Silophant » April 15th, 2018, 1:15 pm

I believe so. As I understand it, the beg buttons have to be at the far side of the crosswalk from their parallel street, and that's where the speakers for the audio cues have to be located. At least, that's the explanation I got for why the new Nicollet crosswalks have beg buttons (that can't actually be pressed, because the walk signs always come on) on separate poles from the actual stoplights, even though the stoplight poles have covered cutouts that are very clearly intended to be where the beg buttons are mounted.

David Greene
IDS Center
Posts: 4691
Joined: December 4th, 2012, 11:41 am

Re: RE: Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby David Greene » April 15th, 2018, 2:33 pm


thatchio wrote:If there were ever a subway, there would likely be only one station in between Loring Park and Uptown Transit Center. Stations are expensive. That said, aBRT is not as capital intensive. Things to consider: how should surface transit operate in this section, especially if there are both local and aBRT routes? aBRT will need to occasionally pass local buses.

I would hope that Hennepin improvements would include at least:
- removal of the bus stops at 28th and 22nd
Agree with everything you said except this. There's a senior mid-rise at that intersection. I'd prefer a stop there rather than at 27th. Yes, it's close to the transit center but the disproportionate number of transit-dependent people there justifies it.

Bus-only lanes should go all the way to Lake. Opening then to carpools would also be fine. They would need to be enforced.

Sent from my Nexus 5X using Tapatalk


thatchio
Nicollet Mall
Posts: 180
Joined: August 2nd, 2012, 6:49 am

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby thatchio » April 15th, 2018, 9:19 pm

Point taken about the audio-alerting functions of the beg button. I was intending more that one shouldn't have to press the button to get a walk.

As for 28th bus stop, it'd be useful to get some data on how many mobility restricted individuals use it. I found that stop extremely frustrating as it rarely seemed to have seniors or others with clear mobility needs. Minneapolis has far too many bus stops in general. Makes the 6 extremely frustrating to use if you're going south of Uptown. If I were to be more bold, I'd say get rid of stops at 22nd, 25th (except if that's where the E line stop is), 28th, and Lake Street. If 25th is for the E, then get rid of 22nd, 24th, and 26th, and keeping 27th.

User avatar
Anondson
Capella Tower
Posts: 3330
Joined: July 21st, 2013, 8:57 pm
Location: Where West Minneapolis Once Was

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby Anondson » April 16th, 2018, 10:31 am

Not to continue the tangent, but how do countries that don’t have the ADA handle handicap accessibility at pedestrian crossings for the blind?

David Greene
IDS Center
Posts: 4691
Joined: December 4th, 2012, 11:41 am

Re: Hennepin Avenue Reconstruction / E Line (Uptown to Downtown)

Postby David Greene » April 16th, 2018, 6:18 pm

I guess it depends on the definition of "mobility limited." Many such people don't have obvious physical disabilities. I'd like to see data too. More may use the stop off-peak, which I don't have a lot of anecdata about.

Sent from my Nexus 5X using Tapatalk