Orange Line / 35W@94: Downtown to Crosstown Project

Roads - Rails - Sidewalks - Bikeways
HiawathaGuy
Wells Fargo Center
Posts: 1612
Joined: June 4th, 2012, 12:03 pm

Re: Orange Line / 35W@94: Downtown to Crosstown Project

Postby HiawathaGuy » September 26th, 2019, 7:27 pm

Korh wrote:
September 26th, 2019, 8:56 am
Just heard that the 4th Avenue and 10th Street to I-35W southbound ramp is opening today 2 years ahead of schedule.
Didn't have a chance to get the full story this morning so anyone know more detail about it and how it effects the rest of the project?
http://www.startribune.com/key-ramp-to- ... 561313712/

amiller92
Wells Fargo Center
Posts: 1828
Joined: October 31st, 2014, 12:50 pm

Re: Orange Line / 35W@94: Downtown to Crosstown Project

Postby amiller92 » September 27th, 2019, 9:15 am

Don't normally recommend tv news, but this one has comments from some bozo who biked over to check out the pedestrian bring that's supposed to open ahead of schedule too: https://www.fox9.com/news/ramp-from-dow ... f-schedule

NickP
Rice Park
Posts: 406
Joined: June 4th, 2012, 5:00 pm

Re: Orange Line / 35W@94: Downtown to Crosstown Project

Postby NickP » September 28th, 2019, 9:17 am

Nice man!

mulad
Moderator
Posts: 2751
Joined: June 4th, 2012, 6:30 pm
Location: Saint Paul
Contact:

Re: Orange Line / 35W@94: Downtown to Crosstown Project

Postby mulad » October 26th, 2019, 6:14 pm

Here's a Channel 9 article on the bus tunnel that's going to go in by the I-35W/I-494 interchange, which has a couple renderings:
https://www.fox9.com/news/four-years-of ... nterchange

It's not entirely clear when buses might start using the tunnel. That article says December 2021, though that might just be the overall Orange Line target date. Here's another article from the Sun Current:
https://www.hometownsource.com/sun_curr ... 8809a.html

DanPatchToget
US Bank Plaza
Posts: 755
Joined: March 30th, 2016, 1:26 pm

Re: Orange Line / 35W@94: Downtown to Crosstown Project

Postby DanPatchToget » October 26th, 2019, 7:49 pm

And it was only a few years ago I saw 2019 as the intended opening year. Maybe they should just say "we don't know" when asked when it'll open, or put TBD for startup year. That way they don't have to try to dance around the fact that they're a couple years off schedule.

Rant over.

SurlyLHT
Foshay Tower
Posts: 845
Joined: February 21st, 2017, 3:50 pm

Re: Orange Line / 35W@94: Downtown to Crosstown Project

Postby SurlyLHT » February 20th, 2020, 11:12 am

I found it interesting that within the Strib article below they state that MnDot is spending $68 million on stormwater. Motorists passing by the construction probably don't realize that part of what is going on is spending money to protect the highway from climate change.

http://www.startribune.com/weekend-warm ... fresh=true

Online
Silophant
Moderator
Posts: 3909
Joined: June 20th, 2012, 4:33 pm
Location: The Gateway

Re: Orange Line / 35W@94: Downtown to Crosstown Project

Postby Silophant » February 20th, 2020, 11:27 am

Very cool that the usual suspects in the comments are furious that the state is spending money trying to keep their highway from flooding.

SurlyLHT
Foshay Tower
Posts: 845
Joined: February 21st, 2017, 3:50 pm

Re: Orange Line / 35W@94: Downtown to Crosstown Project

Postby SurlyLHT » February 20th, 2020, 12:09 pm

35W would make a lovely seasonal canal every Spring. We could water ski and everything. Form a festival around it.

Korh
Nicollet Mall
Posts: 175
Joined: March 8th, 2017, 10:21 pm

Re: Orange Line / 35W@94: Downtown to Crosstown Project

Postby Korh » July 27th, 2020, 7:39 pm

Anyone know how much has the project progressed in the past few months?
Cause just if it's still expected to open in 2021 I wonder if it might end up underperforming more than the red line did when it started service.

Tcmetro
Wells Fargo Center
Posts: 1401
Joined: May 31st, 2012, 8:02 pm
Location: Chicago (ex-Minneapolitan)

Re: Orange Line / 35W@94: Downtown to Crosstown Project

Postby Tcmetro » July 27th, 2020, 8:50 pm

There was originally supposed to be connecting bus plans published for public hearing this spring. That was withdrawn, and I haven't seen anything since.

I would imagine the Lake St and 494 projects are still underway. The other stations would probably be able to be built next year and still meet the end of 2021 timeline.

DanPatchToget
US Bank Plaza
Posts: 755
Joined: March 30th, 2016, 1:26 pm

Re: Orange Line / 35W@94: Downtown to Crosstown Project

Postby DanPatchToget » July 27th, 2020, 9:27 pm

Work on the platforms at South Bloomington Transit Center began a month or so ago.

MNdible
is great.
Posts: 5734
Joined: June 8th, 2012, 8:14 pm
Location: Minneapolis

Re: Orange Line / 35W@94: Downtown to Crosstown Project

Postby MNdible » July 28th, 2020, 10:23 am

Yes, the Lake Street station is really starting to take shape now, and this summer's closures at 494 are related to the construction of the Knox Ave tunnel, as near as I can tell.