Re: Southwest LRT (Green Line Extension)

Postby tmart » May 31st, 2018, 1:05 pm

394 was included in the highway BRT study a few years ago. 2013 cost was estimated at $47m, which is a bargain compared to the cost of LRT here.
The reason it was estimated so cheaply is because MNDOT views BRT as "any bus with expensive shelters and an abstract route map." The studied plan had $0 for corridor construction and $0 for right-of-way. It was using shoulders at rush hour and mixed-traffic otherwise, all but 3 eastbound and 1 westbound stations were completely offline, and even the "inline" ones were only adjacent to the highway and still involved exiting. This does not satisfy any definition of rapid transit.

mattaudio
Stone Arch Bridge
Posts: 7752
Joined: June 19th, 2012, 2:04 pm
Location: NORI: NOrth of RIchfield

Re: Southwest LRT (Green Line Extension)

Postby mattaudio » May 31st, 2018, 1:49 pm

Yeah, I was going to say... Have people even seen the Red Line?

EOst
Capella Tower
Posts: 2424
Joined: March 19th, 2014, 8:05 pm
Location: Saint Paul

Re: Southwest LRT (Green Line Extension)

Postby EOst » May 31st, 2018, 2:34 pm

The reason it was estimated so cheaply is because MNDOT views BRT as "any bus with expensive shelters and an abstract route map." The studied plan had $0 for corridor construction and $0 for right-of-way. It was using shoulders at rush hour and mixed-traffic otherwise, all but 3 eastbound and 1 westbound stations were completely offline, and even the "inline" ones were only adjacent to the highway and still involved exiting. This does not satisfy any definition of rapid transit.
Okay, but increase the cost fivefold for station/corridor improvements and it's still a fraction of what LRT would cost here. The 394 HOT lanes make a natural BRT corridor.

Bakken2016
Wells Fargo Center
Posts: 1019
Joined: September 20th, 2017, 12:40 pm
Location: North Loop

Re: Southwest LRT (Green Line Extension)

Postby Bakken2016 » May 31st, 2018, 3:19 pm

Met Council approved new budget for SWLRT yesterday, and Hennepin County and HCRR just approved the additional money to cover the difference.

tmart
Rice Park
Posts: 488
Joined: October 6th, 2017, 10:05 am
Location: Expat

Re: Southwest LRT (Green Line Extension)

Postby tmart » May 31st, 2018, 3:27 pm

So now it basically comes down to the track usage hearings/negotiations and the NIMBY appeal?

Bakken2016
Wells Fargo Center
Posts: 1019
Joined: September 20th, 2017, 12:40 pm
Location: North Loop

Re: Southwest LRT (Green Line Extension)

Postby Bakken2016 » May 31st, 2018, 3:32 pm

So now it basically comes down to the track usage hearings/negotiations and the NIMBY appeal?
Yea, though I have not heard anything about the NIMBY appeal, hopefully they gave up.

Multimodal
US Bank Plaza
Posts: 724
Joined: March 4th, 2016, 7:55 am
Location: Oh, no, the burbs!

Re: Southwest LRT (Green Line Extension)

Postby Multimodal » June 4th, 2018, 9:51 pm

The median-located BART stations were totally fine when I used to take it. They did a great job on designing the stations to be real enclosed buildings just like any other station. They're not super walkable locations, true, but they're pretty busy even if they are park-and-rides.

It does have its drawbacks, but when our growth and development has happened along these corridors for decades, then sometimes going where the people are involves making those compromises. I think 394 is probably the top candidate where it could actually make sense in MN.
And with the recent propensity for suggesting highway caps, and with all the density added along corridors before ground has even broken along SWLRT (SLP, Hopkins, etc.), highways like 394 & 100 with their built-in ROW make more and more sense every day.

Imagine stations, highway caps, and added density at 394 & Penn/Cedar Lake; at 100 & the West End; at 100 & 50th/Vernon/Grandview; and at 100 & Pentagon Park/Normandale Lakes.

xandrex
Wells Fargo Center
Posts: 1384
Joined: January 30th, 2013, 11:14 am

Re: Southwest LRT (Green Line Extension)

Postby xandrex » June 5th, 2018, 10:14 am

Freeways caps can be great, but I'm a little skeptical it's feasible where you're suggesting.

394 & Penn/Cedar Lake is in a weird spot where the highway is an elevated bridge with Penn above it. Cedar Lake is low density and park land. 394 is basically at grade near West End.

Multimodal
US Bank Plaza
Posts: 724
Joined: March 4th, 2016, 7:55 am
Location: Oh, no, the burbs!

Re: Southwest LRT (Green Line Extension)

Postby Multimodal » June 5th, 2018, 11:04 pm

394 gets elevated east of Penn, right? I’m thinking of the area between Penn & Cedar Lake (so, west of Penn). We reconnect Cedar Lake Rd. on both sides of 394. Bryn Mawr gets reconnected to the lost neighborhood to its south, and the density already along 394 gets built up. If 394 is at-grade here, then use Elon’s magical Boring Company to drive 394 (and trains) underground here.

Same with the West End. Have you ever tried to bike there? Between 394, 100, and the railroad, it’s very hard to get there other than by very circuitous routes. I live southeast of there, and I biked there once and never again. Here again (since we’re fantasizing about rail on highway right of way), we could use the Boring Company to tunnel Hwy 100 (and transit) underground, reconnecting neighborhoods (and another segment of Cedar Lake Road!).

OK, so maybe it’s technically not a cap. But the point is that density is naturally occurring along transportation routes, whether sea, river, rail, or highway. So putting new rail along highway ROW, adding density, and reconnecting neighborhoods makes a lot of sense.

tmart
Rice Park
Posts: 488
Joined: October 6th, 2017, 10:05 am
Location: Expat

Re: Southwest LRT (Green Line Extension)

Postby tmart » June 6th, 2018, 11:06 am

Yeah, the jist of this I agree with. (I don't know why Elon needs to come into this--we've been able to put rails and roads underground for a century and we simply lack the motivation.)

Like it or not, outside of the cities and the first-tier suburbs, our development happened around these freeways, a lot of which are already slightly below grade. The question then becomes how the goals of transit, efficiency, and environmentalism can adapt to that reality, and I think the combination of highway-running transit and judicious use of caps and infill development to beef up and connect the station-adjacent areas is the best I've heard or come up with.

DanPatchToget
Wells Fargo Center
Posts: 1645
Joined: March 30th, 2016, 1:26 pm

Re: Southwest LRT (Green Line Extension)

Postby DanPatchToget » June 14th, 2018, 9:19 pm

http://www.startribune.com/southwest-li ... 485623731/

Hopkins O&M facility being scaled back to cut costs. Or they could just, you know, scrap the stupid tunnel in Kenilworth.

Bakken2016
Wells Fargo Center
Posts: 1019
Joined: September 20th, 2017, 12:40 pm
Location: North Loop

Re: Southwest LRT (Green Line Extension)

Postby Bakken2016 » June 14th, 2018, 9:26 pm

http://www.startribune.com/southwest-li ... 485623731/

Hopkins O&M facility being scaled back to cut costs. Or they could just, you know, scrap the stupid tunnel in Kenilworth.
This in my opinion is a good idea, we have two O&M’s already, to save $70 mil this was a good cut to the project.


Sent from my iPhone using Tapatalk

Bakken2016
Wells Fargo Center
Posts: 1019
Joined: September 20th, 2017, 12:40 pm
Location: North Loop

Re: Southwest LRT (Green Line Extension)

Postby Bakken2016 » July 13th, 2018, 7:52 pm

[IMG]//uploads.tapatalk-cdn.com/201807 ... 179922.png[/IMG]

Looks like TCWR and Met Council have come to an agreement?


Sent from my iPhone using Tapatalk

Qhaberl
Foshay Tower
Posts: 855
Joined: February 25th, 2016, 9:51 am

Re: Southwest LRT (Green Line Extension)

Postby Qhaberl » July 14th, 2018, 7:04 am

So if they have settled, when will shovels hit the ground? Did we secure the Federal matching funds? I know that there was a second round of bids. Were any of those bids selected?


Sent from my iPhone using Tapatalk

Tcmetro
Wells Fargo Center
Posts: 1768
Joined: May 31st, 2012, 8:02 pm
Location: Chicago (ex-Minneapolitan)

Re: Southwest LRT (Green Line Extension)

Postby Tcmetro » July 14th, 2018, 9:54 am

I poked around on the Met Council procurement page. The award is still pending. There were two bidders:

- Lunda/CS McCrossan - $799.5 Million
- Ames Kraemer - $812.13 Million

According to the Strib, the first try attracted four bidders, with ranges from $797-1080 M.

http://www.startribune.com/new-bids-for ... 481688121/
http://www.startribune.com/met-council- ... 446218353/

I don't think we will hear anything for another month at least. The July Corridor Management Committee meeting was canceled.

DanPatchToget
Wells Fargo Center
Posts: 1645
Joined: March 30th, 2016, 1:26 pm

Re: Southwest LRT (Green Line Extension)

Postby DanPatchToget » July 16th, 2018, 11:29 am

http://www.startribune.com/key-southwes ... 488298531/

The good news: Agreement with TC&W

The bad news: A 2 month delay (not that that's surprising anymore)

The worse news: The Star Tribune sucks at editing and fact checking

Bakken2016
Wells Fargo Center
Posts: 1019
Joined: September 20th, 2017, 12:40 pm
Location: North Loop

Re: Southwest LRT (Green Line Extension)

Postby Bakken2016 » July 16th, 2018, 11:34 am

http://www.startribune.com/key-southwes ... 488298531/

The good news: Agreement with TC&W

The bad news: A 2 month delay (not that that's surprising anymore)

The worse news: The Star Tribune sucks at editing and fact checking
I'm just like "I wish it was still opening in 2021."

User avatar
jtoemke
Landmark Center
Posts: 252
Joined: March 5th, 2015, 8:04 am
Location: Columbus OH

Re: Southwest LRT (Green Line Extension)

Postby jtoemke » July 16th, 2018, 11:44 am

http://www.startribune.com/key-southwes ... 488298531/

The good news: Agreement with TC&W

The bad news: A 2 month delay (not that that's surprising anymore)

The worse news: The Star Tribune sucks at editing and fact checking
That last sentence... "The $2 billion, 14.5-million line will run from downtown Minneapolis to Eden Prairie beginning service in 2021."

omg.

HiawathaGuy
Wells Fargo Center
Posts: 1636
Joined: June 4th, 2012, 12:03 pm

Re: Southwest LRT (Green Line Extension)

Postby HiawathaGuy » July 17th, 2018, 9:18 am


gopherfan
Nicollet Mall
Posts: 129
Joined: January 15th, 2013, 5:09 pm

Re: Southwest LRT (Green Line Extension)

Postby gopherfan » July 18th, 2018, 8:09 am

Pretty good info about the agreement here. Council to pay $18.5M to remove their existing siding track over 5 years. Then the council will own the corridors and be responsible for maintenance and liabilities, however TCWR will pay council fees for maintenance (undisclosed amount). In terms of liability, Met Council will be responsible for any LRT claims, and TCWR will be responsible for any rail ONLY claims. Ie. if there's a derailment that involves LRT, sounds like the council would be paying claims...
https://metrocouncil.org/Council-Meetin ... 80718.aspx