Southwest LRT (Green Line Extension)

Roads - Rails - Sidewalks - Bikeways
Bakken2016
Union Depot
Posts: 314
Joined: September 20th, 2017, 12:40 pm
Location: North Loop

Re: Southwest LRT (Green Line Extension)

Postby Bakken2016 » July 26th, 2018, 2:06 pm

http://www.startribune.com/southwest-lr ... 489174021/

The Star Tribune Editorial Board believes that if Rep Erik Paulsen supports SWLRT, than there would not be a slow down of funds.

User avatar
VacantLuxuries
US Bank Plaza
Posts: 650
Joined: February 20th, 2015, 12:38 pm

Re: Southwest LRT (Green Line Extension)

Postby VacantLuxuries » July 26th, 2018, 3:03 pm

Christ, if that's where we are...

Better to replace him with Dean Phillips. I wouldn't trust Paulsen to keep his word.

Tom H.
Rice Park
Posts: 413
Joined: September 4th, 2012, 5:23 am

Re: Southwest LRT (Green Line Extension)

Postby Tom H. » August 16th, 2018, 2:09 pm

The Culver's location at Southwest Station is relocating to an outlot in the nearby Lund's & Byerly's parking lot. The current Culver's location is planned to be demolished for the SWLRT project, so this seems like an indication that ROW acquisition is moving forward, at least.

Bakken2016
Union Depot
Posts: 314
Joined: September 20th, 2017, 12:40 pm
Location: North Loop

Re: Southwest LRT (Green Line Extension)

Postby Bakken2016 » August 24th, 2018, 11:06 am

http://www.southwestjournal.com/news/tr ... een-light/

Surface Transportation Board has given Met Council the green light to acquire the railroad land.

So basically all that is left is a letter of no prejudice to start building with local funds, and then applying for the federal grant money.

Bakken2016
Union Depot
Posts: 314
Joined: September 20th, 2017, 12:40 pm
Location: North Loop

Re: Southwest LRT (Green Line Extension)

Postby Bakken2016 » August 30th, 2018, 2:58 pm

https://minnlawyer.com/2018/08/29/met-c ... usinesses/

Estimating 25-30 business owners may claim a "loss of going concern"

Does that refer to the business thinking they might go under do to the construction?

User avatar
Anondson
Capella Tower
Posts: 3484
Joined: July 21st, 2013, 8:57 pm
Location: Where West Minneapolis Once Was

Re: Southwest LRT (Green Line Extension)

Postby Anondson » September 27th, 2018, 11:47 am

An update on the archeological dig at Royalston sites from this past summer.

https://metrocouncil.org/News-Events/Tr ... -focu.aspx

DanPatchToget
Rice Park
Posts: 470
Joined: March 30th, 2016, 1:26 pm

Re: Southwest LRT (Green Line Extension)

Postby DanPatchToget » September 27th, 2018, 4:30 pm

What happened to the issue over the railroad historic district or whatever the hell it was called? The area that's just gravel pits, an impound lot, a train track, a trail, and a crumbling retaining wall.

Why were they required to dig only at Royalston and not other places, or the entire route?

Bakken2016
Union Depot
Posts: 314
Joined: September 20th, 2017, 12:40 pm
Location: North Loop

Re: Southwest LRT (Green Line Extension)

Postby Bakken2016 » September 30th, 2018, 10:42 am

http://www.southwestjournal.com/news/tr ... -contract/

Delayed by another 45 days for the contract since the FTA hasn’t issued the Letter of No Predijuce yet.

Oreos&Milk
Metrodome
Posts: 52
Joined: February 11th, 2018, 11:51 am

Re: Southwest LRT (Green Line Extension)

Postby Oreos&Milk » October 1st, 2018, 1:40 pm

Are we great yet? :oops:

Bakken2016
Union Depot
Posts: 314
Joined: September 20th, 2017, 12:40 pm
Location: North Loop

Re: Southwest LRT (Green Line Extension)

Postby Bakken2016 » October 3rd, 2018, 3:51 pm

http://www.southwestjournal.com/news/tr ... ction-job/

Ames Construction and Kraemer North America dropped out, leaving only the $799.5 million Lunda-McCrossan bid. Which is the cheaper one.

bubzki2
US Bank Plaza
Posts: 664
Joined: September 19th, 2012, 5:38 pm
Location: Merriam Park

Re: Southwest LRT (Green Line Extension)

Postby bubzki2 » October 4th, 2018, 8:55 am


tmart
Landmark Center
Posts: 270
Joined: October 6th, 2017, 10:05 am
Location: Expat

Re: Southwest LRT (Green Line Extension)

Postby tmart » October 4th, 2018, 9:18 am

It's not great, but I'm more worried about the FTA dragging its feet.

User avatar
VacantLuxuries
US Bank Plaza
Posts: 650
Joined: February 20th, 2015, 12:38 pm

Re: Southwest LRT (Green Line Extension)

Postby VacantLuxuries » October 4th, 2018, 9:31 am

Is the FTA even an agency where there's a way to petition or call to bother them into actually working?

twinkess
Rice Park
Posts: 412
Joined: November 26th, 2012, 10:46 am

Re: Southwest LRT (Green Line Extension)

Postby twinkess » October 4th, 2018, 5:55 pm

a writ of mandamus?


Return to “Transportation”

Who is online

Users browsing this forum: No registered users and 1 guest