Alia Tower - 200 Central - 483' / 40 Stories

Northeast, Near North, Camden, Old St. Anthony, University and surrounding neighborhoods
HiawathaGuy
Wells Fargo Center
Posts: 1636
Joined: June 4th, 2012, 12:03 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby HiawathaGuy » November 23rd, 2016, 12:42 pm

Judge temporarily blocks Alatus LLC’s condo project
http://finance-commerce.com/2016/11/jud ... o-project/

Court date set for December 16, 2016.

mattaudio
Stone Arch Bridge
Posts: 7760
Joined: June 19th, 2012, 2:04 pm
Location: NORI: NOrth of RIchfield

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby mattaudio » November 23rd, 2016, 3:14 pm

Shouldn't they need to put up a surety bond?

amiller92
Wells Fargo Center
Posts: 1984
Joined: October 31st, 2014, 12:50 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby amiller92 » November 23rd, 2016, 3:51 pm

And again, our historical preservation laws are nonsensical and undemocratic.

Silophant
Moderator
Posts: 4482
Joined: June 20th, 2012, 4:33 pm
Location: Whimsical NE

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby Silophant » November 23rd, 2016, 6:43 pm

But for real, why didn't they demolish the building at any point in the last six months or whatever that they've had the permit to do so?
Joey Senkyr
[email protected]

bapster2006
Foshay Tower
Posts: 913
Joined: November 17th, 2012, 6:53 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby bapster2006 » November 23rd, 2016, 7:15 pm

That is exactly what I have been thinking since the day the demolition was approved. I could not figure out why they didn't have equipment out there the next day. At least prepare the site when you had legal permission to do so.

thesilverpen
Block E
Posts: 11
Joined: March 4th, 2016, 7:38 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby thesilverpen » November 25th, 2016, 7:27 am

So... how many times has Alatus said that they "expect to start construction in a couple months"? My guess is they can't get financing... Banks that would consider a (comparatively) small local sponsor, such as Lux, are already over invested in the market in general, and larger lenders or out of town money won't get on board with the current condo construction defect laws that are in place.
They can't get financing... that's why they aren't starting. Everything else is just an excuse or a delay tactic until they (hopefully) get project financing and save face.

seanrichardryan
IDS Center
Posts: 4092
Joined: June 3rd, 2012, 9:33 pm
Location: Merriam Park, St. Paul

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby seanrichardryan » December 2nd, 2016, 11:41 am

Demolition delayed for old funeral home building near downtown Minneapolis
http://www.startribune.com/real-estate- ... 404100036/
Q. What, what? A. In da butt.

twincitizen
Moderator
Posts: 6382
Joined: May 31st, 2012, 7:27 pm
Location: Standish-Ericsson

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby twincitizen » December 2nd, 2016, 11:56 am

Yeah I don't know why anyone thought Alatus would spend any money on demolition or construction when they have been well aware this lawsuit was forthcoming.
Chris Osmundson, development director for Alatus, said that demolition was supposed to start on Nov. 22, but it was suspended to wait for the court hearing.

Hennepin County District Judge Daniel Moreno is scheduled to hear the complaint on Dec. 23.

grant1simons2
IDS Center
Posts: 4371
Joined: February 8th, 2014, 11:33 pm
Location: Marcy-Holmes

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby grant1simons2 » December 23rd, 2016, 11:47 am

Is there anyway to see how this went?

seanrichardryan
IDS Center
Posts: 4092
Joined: June 3rd, 2012, 9:33 pm
Location: Merriam Park, St. Paul

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby seanrichardryan » December 23rd, 2016, 2:50 pm

Q. What, what? A. In da butt.

grant1simons2
IDS Center
Posts: 4371
Joined: February 8th, 2014, 11:33 pm
Location: Marcy-Holmes

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby grant1simons2 » December 23rd, 2016, 3:19 pm

Glad that our legal system is being put to good use. This will never be built now.

User avatar
jtoemke
Landmark Center
Posts: 252
Joined: March 5th, 2015, 8:04 am
Location: Columbus OH

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby jtoemke » December 23rd, 2016, 3:25 pm

This is across the river from downtown and near to other very tall buildings. This is so ridiculous that it can be held up like this. It got approval. Tear it down in the dead of night and deal with the consequences later.

I know thats not how it works, but its just frustrating. Its alongside a massive parking garage and a 12 story building, not in the middle of some neighborhood.

TroyGBiv
US Bank Plaza
Posts: 658
Joined: July 6th, 2012, 10:33 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby TroyGBiv » March 4th, 2017, 1:10 am

March is when this goes to court...

spearson
Landmark Center
Posts: 291
Joined: July 9th, 2012, 2:29 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby spearson » March 6th, 2017, 10:25 am

If this continues on as planned, can Alatus counter sue the neighborhood group for any increases in cost due to their appeal?

MNdible
is great.
Posts: 5997
Joined: June 8th, 2012, 8:14 pm
Location: Minneapolis

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby MNdible » March 6th, 2017, 10:43 am

Didn't the official neighborhood group actually support the project?

grant1simons2
IDS Center
Posts: 4371
Joined: February 8th, 2014, 11:33 pm
Location: Marcy-Holmes

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby grant1simons2 » March 6th, 2017, 3:22 pm

Yes

Qhaberl
Foshay Tower
Posts: 855
Joined: February 25th, 2016, 9:51 am

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby Qhaberl » March 7th, 2017, 4:51 am

Were you saying yes to post #594 Or #595?


Sent from my iPhone using Tapatalk

bubzki2
Foshay Tower
Posts: 811
Joined: September 19th, 2012, 5:38 pm
Location: Snelling-Hamline

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby bubzki2 » March 7th, 2017, 8:01 am

Cost reimbursement (e.g., attorneys fees, etc.) for the suit are basically up to the judge to decide.

Qhaberl
Foshay Tower
Posts: 855
Joined: February 25th, 2016, 9:51 am

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby Qhaberl » March 7th, 2017, 9:46 am

Let's say the judge allows the development to proceed, anyone have any idea as to how long we might wait before construction actually commences?


Sent from my iPhone using Tapatalk

twincitizen
Moderator
Posts: 6382
Joined: May 31st, 2012, 7:27 pm
Location: Standish-Ericsson

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby twincitizen » March 7th, 2017, 10:37 am

Still a mystery to anyone not involved in the project. They aren't doing condo pre-sales at all, which is unusual, so are they still lining up financing? Self-financing? (unlikely for a project this costly) Who knows? We really haven't heard much about how this project will be financed.

As far as I know, Alatus didn't push back against the lengthy court timeline for trial (March date was set back in December). Presumably they could have petitioned the court to hear the case sooner, but I didn't see any media reports of that happening, so I can only assume they're comfortable with this delay and never had any intention of breaking ground before Spring/Summer 2017 anyways.
While the March 13 trial date will effectively delay any start to the project until at least this spring, representatives for Alatus said Friday they believe the overall project timeline is not yet impacted by the lawsuit.
“We feel like from a project schedule standpoint this is the most expedient way to deal with this [lawsuit] and stay on our timeline” for delivering the project, Chris Osmundson, development director for Alatus, said in an interview after the hearing on Friday.


Who is online