Alia Tower - 200 Central - 483' / 40 Stories

Northeast, Near North, Camden, Old St. Anthony, University and surrounding neighborhoods
bapster2006
Foshay Tower
Posts: 913
Joined: November 17th, 2012, 6:53 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby bapster2006 » March 20th, 2017, 12:20 pm

An Order dismissing the Plaintiff's (NEBL) claim relating to the MERA (MN Environmental Rights Act) has been signed by the judge. This was NEBL's primary argument. The parties have agreed to this.

The next order will relate to whether the demolition will be granted.

User avatar
jtoemke
Landmark Center
Posts: 252
Joined: March 5th, 2015, 8:04 am
Location: Columbus OH

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby jtoemke » March 20th, 2017, 1:49 pm

Good news

grant1simons2
IDS Center
Posts: 4371
Joined: February 8th, 2014, 11:33 pm
Location: Marcy-Holmes

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby grant1simons2 » March 26th, 2017, 2:24 pm

Trial has been cancelled. But these people won't rest.

http://stopalatus.blogspot.com/

Qhaberl
Foshay Tower
Posts: 855
Joined: February 25th, 2016, 9:51 am

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby Qhaberl » March 27th, 2017, 6:52 am

If the trial has been canceled, doesn't that mean they can go ahead with demolition/construction?


Sent from my iPhone using Tapatalk

bapster2006
Foshay Tower
Posts: 913
Joined: November 17th, 2012, 6:53 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby bapster2006 » March 27th, 2017, 7:00 am

The court is reviewing each decision separately, so the demolition was the latest to be reviewed and the Order will be signed hopefully anytime now.

Qhaberl
Foshay Tower
Posts: 855
Joined: February 25th, 2016, 9:51 am

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby Qhaberl » March 27th, 2017, 8:27 am

So once the demolition order is signed, then domolish it right away?


Sent from my iPhone using Tapatalk

bapster2006
Foshay Tower
Posts: 913
Joined: November 17th, 2012, 6:53 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby bapster2006 » March 27th, 2017, 9:35 am

I just saw the Order signed by the Judge stating that Alatus and the city correctly followed all procedures allowing for the demolition of the commercial club and construction of a new tower. The counts relating to NEBL's complaints are dismissed.

Take THAT StarTribune and Business Journal.

Qhaberl
Foshay Tower
Posts: 855
Joined: February 25th, 2016, 9:51 am

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby Qhaberl » March 27th, 2017, 10:19 am

That's excellent! Now they need to get this thing demolished before any other group decides to try and stop it. This will be a beautiful tower. I will be able to see the construction of it from my living room window.


Sent from my iPhone using Tapatalk

TroyGBiv
US Bank Plaza
Posts: 658
Joined: July 6th, 2012, 10:33 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby TroyGBiv » March 27th, 2017, 12:50 pm

The NeBL funding push continues to try to raise the rest of the money they're owe the lawyer... there aren't any other options to try to stop this project.

amiller92
Wells Fargo Center
Posts: 1983
Joined: October 31st, 2014, 12:50 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby amiller92 » March 27th, 2017, 1:00 pm

There is always appeal.

Qhaberl
Foshay Tower
Posts: 855
Joined: February 25th, 2016, 9:51 am

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby Qhaberl » March 27th, 2017, 1:50 pm

How long is the development company have to wait until they can demolish? I guess I am asking, how long do they have to wait for an appeal to be filed? Let's say, hypothetically, if they tear down the old building tomorrow, then there's no need for an appeal. The job is already done.


Sent from my iPhone using Tapatalk

amiller92
Wells Fargo Center
Posts: 1983
Joined: October 31st, 2014, 12:50 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby amiller92 » March 27th, 2017, 2:02 pm

Unless the judge (or appeals panel) issues a stay, they don't have to wait at all.

bapster2006
Foshay Tower
Posts: 913
Joined: November 17th, 2012, 6:53 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby bapster2006 » March 29th, 2017, 10:16 am

Judgment was entered today. Of course, the parties could agree to hold the demolition for now, but given that NEBL has raised $100 for appeal, I don't think that is going to be a serious issue.

bapster2006
Foshay Tower
Posts: 913
Joined: November 17th, 2012, 6:53 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby bapster2006 » March 29th, 2017, 12:20 pm


grant1simons2
IDS Center
Posts: 4371
Joined: February 8th, 2014, 11:33 pm
Location: Marcy-Holmes

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby grant1simons2 » March 29th, 2017, 12:23 pm

It says it delays construction?

User avatar
FISHMANPET
IDS Center
Posts: 4241
Joined: June 6th, 2012, 2:19 pm
Location: Corcoran

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby FISHMANPET » March 29th, 2017, 12:47 pm

Specifically it says it "has" delayed construction. My interpretation of that would be that the process overall has delayed the start of construction (which is true) but they're still hoping to start in April.

amiller92
Wells Fargo Center
Posts: 1983
Joined: October 31st, 2014, 12:50 pm

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby amiller92 » March 29th, 2017, 12:50 pm

I went by yesterday afternoon and there were two guys/trucks on site looking around.

Qhaberl
Foshay Tower
Posts: 855
Joined: February 25th, 2016, 9:51 am

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby Qhaberl » March 29th, 2017, 2:17 pm

Can somone copy a link to the most recent planning comission report on this project?


Sent from my iPhone using Tapatalk

nfschauer
Nicollet Mall
Posts: 165
Joined: July 23rd, 2014, 2:52 pm
Location: Highland Park

Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories

Postby nfschauer » March 29th, 2017, 2:26 pm

Last time I walked by the funeral home, I saw piles of wood and demo debris inside, which I did not see a month ago.

User avatar
Nathan
Capella Tower
Posts: 3695
Joined: June 1st, 2012, 10:42 am

Re: Alatus St. Anthony Tower (Washburn-McReavy Site)

Postby Nathan » March 30th, 2017, 10:18 am

I think these were the last submitted plans, Q.
City review packet for June 30:

http://www.ci.minneapolis.mn.us/www/gro ... 182175.pdf

Approximate height about 485 feet