Stick vs. Concrete / Construction Quality Issues

Introductions - Urban Issues - Miscellaneous News, Topics, Interests
grant1simons2
IDS Center
Posts: 4371
Joined: February 8th, 2014, 11:33 pm
Location: Marcy-Holmes

Re: Stick vs. Concrete / Construction Quality Issues

Postby grant1simons2 » March 16th, 2017, 10:46 pm

Raleigh right now. Stick frame building is a blaze.

mattaudio
Stone Arch Bridge
Posts: 7752
Joined: June 19th, 2012, 2:04 pm
Location: NORI: NOrth of RIchfield

Re: Stick vs. Concrete / Construction Quality Issues

Postby mattaudio » March 17th, 2017, 7:08 am

Just came here to post that... Sounds like it was under construction. Five alarm fire, completely destroyed in a few short hours.

It seems like there's a lot of stick-build risk when these buildings are under construction or renovation. But are they at risk when they are sprinklered, partitioned into hundreds of smaller spaces with fire-rated drywall, separated by fire-rated doors, etc? Seems like the risk is just during construction.

mattaudio
Stone Arch Bridge
Posts: 7752
Joined: June 19th, 2012, 2:04 pm
Location: NORI: NOrth of RIchfield

Re: Stick vs. Concrete / Construction Quality Issues

Postby mattaudio » August 18th, 2017, 2:09 pm

Apartment Fires Are Tied to Cheaper, Wood-Based Construction
Blazes at construction sites raise questions about use of wooden frames instead of higher-cost metal ones
https://www.theatlantic.com/business/ar ... nt/532437/

MNdible
is great.
Posts: 5989
Joined: June 8th, 2012, 8:14 pm
Location: Minneapolis

Re: Stick vs. Concrete / Construction Quality Issues

Postby MNdible » August 18th, 2017, 3:07 pm


twincitizen
Moderator
Posts: 6368
Joined: May 31st, 2012, 7:27 pm
Location: Standish-Ericsson

Re: Stick vs. Concrete / Construction Quality Issues

Postby twincitizen » March 12th, 2018, 9:02 am

Question: what's the average time from groundbreaking to completion & occupancy of a stick project with underground parking? Does 4 stories vs. 6 stories make a major impact on the timeline, or is that just a few extra weeks? How about smaller projects without underground parking, like the 3535 Grand Ave S project?

The reason for my question is related to the 2020 Census. What is the absolute latest that a project with underground parking could begin construction and be occupied on April 1, 2020? For the purposes of this inquiry, I'm not considering large tower projects like 200 Central and The Eleven...we already know those won't be occupied by Census day.

User avatar
VacantLuxuries
Foshay Tower
Posts: 973
Joined: February 20th, 2015, 12:38 pm

Re: Stick vs. Concrete / Construction Quality Issues

Postby VacantLuxuries » March 12th, 2018, 9:20 am

An older article but might still be relevant

http://eyeonhousing.org/2015/08/how-lon ... -building/

twincitizen
Moderator
Posts: 6368
Joined: May 31st, 2012, 7:27 pm
Location: Standish-Ericsson

Re: Stick vs. Concrete / Construction Quality Issues

Postby twincitizen » March 13th, 2018, 11:30 am

Thanks. It looks like 16-18 months is pretty typical for a larger (50+ unit) project, which squares with what I've heard around here.

So for a 4-6 story 50+ unit building to have residents moving in by 4/1/2020 (Census Day), they'd need to be excavating no later than October/November of this year. Good to know.

MNdible
is great.
Posts: 5989
Joined: June 8th, 2012, 8:14 pm
Location: Minneapolis

Re: Stick vs. Concrete / Construction Quality Issues

Postby MNdible » March 13th, 2018, 12:18 pm

Also, remember that most buildings aren't going to be fully occupied on opening day -- there's typically a gradual lease-up over six months or so.

John21
Rice Park
Posts: 449
Joined: June 8th, 2012, 8:23 am
Location: 38th Street Station

Re: Stick vs. Concrete / Construction Quality Issues

Postby John21 » February 13th, 2019, 9:02 am


Bob Stinson's Ghost
Landmark Center
Posts: 264
Joined: January 20th, 2018, 11:36 pm

Re: Stick vs. Concrete / Construction Quality Issues

Postby Bob Stinson's Ghost » February 13th, 2019, 10:58 am

And there are echoes in at least some of the agitation of standard-variety Nimbyism.

Anondson
IDS Center
Posts: 4645
Joined: July 21st, 2013, 8:57 pm
Location: Where West Minneapolis Once Was

Re: Stick vs. Concrete / Construction Quality Issues

Postby Anondson » May 22nd, 2019, 7:47 pm

Kinda related to the topic, a startup with a model for modular construction of apartments and hotels.

https://www.bizjournals.com/twincities/ ... costs.html

Seems like a necessary but very late thing.

twincitizen
Moderator
Posts: 6368
Joined: May 31st, 2012, 7:27 pm
Location: Standish-Ericsson

Re: Stick vs. Concrete / Construction Quality Issues

Postby twincitizen » July 21st, 2023, 12:57 pm

Milwaukee got a 25-story mass timber apartment building, tallest in the world (for now).
Ascent MKE: https://www.fs.usda.gov/inside-fs/deliv ... ding-opens

I can't imagine it will be much longer before Mpls gets another mass timber building that will top the T3 (Amazon office) in North Loop. Heck, just copy-paste the Ascent onto any open lot downtown.