I was reading through the 2040 TPP update that is supposed to go before the Met Council for approval soon, an update on arterial BRT is included:

- Removal of W 7th St BRT from the plan
- Chicago-Fremont is included as the third line, after Snelling and Penn. Projected cost, $77 million

http://www.metrocouncil.org/METC/files/ ... 4105af.pdf

twincitizen
Moderator
Posts: 6368
Joined: May 31st, 2012, 7:27 pm
Location: Standish-Ericsson

Re: Arterial Transit Corridor Study ("rapid bus")

Postby twincitizen » December 19th, 2014, 1:43 pm

Pages 8-9 of that document (labeled as pages 233-234) just makes me want to eat a bullet.

Met Council TPP: "Here are our key principles for local bus service planning."

Metro Transit SIP: "Here's our new Service Improvement Plan that incorporates none of those principles."

twincitizen
Moderator
Posts: 6368
Joined: May 31st, 2012, 7:27 pm
Location: Standish-Ericsson

Re: Arterial Transit Corridor Study ("rapid bus")

Postby twincitizen » September 26th, 2016, 12:09 pm

Resurrecting this thread after nearly 2 years of silence. I was skimming the draft update to the 2017-2020 TIP and see that the D Line (first time seeing that name in an official Met Council document) is in the TIP, with a planned opening date of 2020/2021 and a tentative budget of $77MM. This hasn't changed from TCmetro's link above (non-working) which penciled in the same numbers 2 years ago.

DRAFT 2017-2020 TIP (link has been fixed)

We'll have to see how things go with the C Line getting fully funded ($36MM total) before we can even dream about this one becoming a reality. $77MM is a lot for a project that won't be getting any money from CTIB. It's pretty much hoping and praying on federal and Met Council money and a big chunk of the ~2018 bonding bill. Other than "it's the busiest bus line in the region", I think it's going to be a real uphill battle to secure that much funding. The City Council and state legislators are going to have to become champions of this specific project for that to happen, and with the long slate of projects ahead of this one (Orange, SW, Bottineau, C Line, streetcar?), there just doesn't seem to be a way this will get political headwinds until some of those are actually under construction. My concern is that the political capacity doesn't exist to even begin paying attention to this project until 2018 at the soonest (when at least Orange, SW, and C will be under construction.) I guess the important thing for the next ~2 years is that the D Line project is funded for study and engineering, which I'm guessing could cost $5MM for a corridor this long.

mattaudio
Stone Arch Bridge
Posts: 7752
Joined: June 19th, 2012, 2:04 pm
Location: NORI: NOrth of RIchfield

Re: Arterial Transit Corridor Study ("rapid bus")

Postby mattaudio » September 26th, 2016, 12:35 pm

Too bad Minneapolis can't cough up $15-20M a year for aBRT. Well, we should.

twincitizen
Moderator
Posts: 6368
Joined: May 31st, 2012, 7:27 pm
Location: Standish-Ericsson

Re: Arterial Transit Corridor Study ("rapid bus")

Postby twincitizen » September 26th, 2016, 1:22 pm

Too bad Minneapolis can't cough up $15-20M a year for aBRT. Well, we should.
I'd settle for $5MM/year even. If you figure opening a Minneapolis-centric aBRT line every other year, beginning with the C Line in 2019 and the D Line in 2021, that would be a $10MM city contribution for each project. That's actually a lot when you assume a big chunk of FTA money will pay for the new buses, a Met Council contribution, the fact that the D Line also runs through Brooklyn Center, Richfield, and Bloomington, etc. Maybe the city contribution could be equivalent to half the cost of the stations inside city limits or something.

Anondson
IDS Center
Posts: 4645
Joined: July 21st, 2013, 8:57 pm
Location: Where West Minneapolis Once Was

Re: Arterial Transit Corridor Study ("rapid bus")

Postby Anondson » September 26th, 2016, 2:29 pm

Is there a end to end map of the D Line?

EOst
Capella Tower
Posts: 2424
Joined: March 19th, 2014, 8:05 pm
Location: Saint Paul

Re: Arterial Transit Corridor Study ("rapid bus")

Postby EOst » September 26th, 2016, 2:43 pm


David Greene
IDS Center
Posts: 4617
Joined: December 4th, 2012, 11:41 am

Re: Arterial Transit Corridor Study ("rapid bus")

Postby David Greene » September 26th, 2016, 2:58 pm

If there was ever a case for a Minneapolis subway, this is it.

talindsay
Wells Fargo Center
Posts: 1533
Joined: September 29th, 2012, 10:41 am

Re: Arterial Transit Corridor Study ("rapid bus")

Postby talindsay » September 26th, 2016, 3:03 pm

If there was ever a case for a Minneapolis subway, this is it.
Indeed. Sadly, we're 40 years too late for that to be even vaguely considered.

Anondson
IDS Center
Posts: 4645
Joined: July 21st, 2013, 8:57 pm
Location: Where West Minneapolis Once Was

Re: Arterial Transit Corridor Study ("rapid bus")

Postby Anondson » September 26th, 2016, 3:24 pm

Thanks EOst!

User avatar
mister.shoes
Wells Fargo Center
Posts: 1294
Joined: November 26th, 2012, 10:22 am

Re: Arterial Transit Corridor Study ("rapid bus")

Postby mister.shoes » September 26th, 2016, 11:46 pm

Skipping right past 48th, I see. Huh.
The problem with being an introvert online is that no one knows you're just hanging out and listening.

mattaudio
Stone Arch Bridge
Posts: 7752
Joined: June 19th, 2012, 2:04 pm
Location: NORI: NOrth of RIchfield

Re: Arterial Transit Corridor Study ("rapid bus")

Postby mattaudio » September 27th, 2016, 9:57 am

We're working on that, but it's tricky. We think they just spaced these stops out without doing much analysis of the land use around them. At a minimum, we'd like to see stops at 48th and 46th (for transfer to the 46).

But it may make sense to try to hit the old streetcar nodes, in addition to the transfer at 46th: 38th, 41st (maybe not?), 44th, 46th (transfer), 48th, 52nd (spliting the Parkway and 53rd nodes).

Clearly they are fine spacing things differently with the 54th and 56th Street stops, or 60th/Chicago to 60th/Portland. Skipping 48th and Chicago is not acceptable.

amiller92
Wells Fargo Center
Posts: 1983
Joined: October 31st, 2014, 12:50 pm

Re: Arterial Transit Corridor Study ("rapid bus")

Postby amiller92 » September 27th, 2016, 11:56 am

Especially because there isn't really a reason to stop at 50th (aside from that's where I'd get it if I decided to walk over there instead of take the 14).

EOst
Capella Tower
Posts: 2424
Joined: March 19th, 2014, 8:05 pm
Location: Saint Paul

Re: Arterial Transit Corridor Study ("rapid bus")

Postby EOst » September 27th, 2016, 12:04 pm

The stop locations are just conceptual. Both the A and the C have seen stations moved from these concepts once planning began in earnest.

Tcmetro
Wells Fargo Center
Posts: 1768
Joined: May 31st, 2012, 8:02 pm
Location: Chicago (ex-Minneapolitan)

Re: Arterial Transit Corridor Study ("rapid bus")

Postby Tcmetro » December 9th, 2016, 12:24 pm


grant1simons2
IDS Center
Posts: 4371
Joined: February 8th, 2014, 11:33 pm
Location: Marcy-Holmes

Re: Arterial Transit Corridor Study ("rapid bus")

Postby grant1simons2 » December 9th, 2016, 6:28 pm

E Line should continue up into University where the 6U already goes. Making the final stop Stadium Village station.

User avatar
nBode
Union Depot
Posts: 348
Joined: August 20th, 2013, 3:25 pm
Location: University of Minnesota

Re: Arterial Transit Corridor Study ("rapid bus")

Postby nBode » December 9th, 2016, 7:26 pm

^agreed

EOst
Capella Tower
Posts: 2424
Joined: March 19th, 2014, 8:05 pm
Location: Saint Paul

Re: Arterial Transit Corridor Study ("rapid bus")

Postby EOst » December 10th, 2016, 8:50 am

Not sure I love the perception of Minneapolis getting SW, Bottineau, Orange, half of A and lines B, C, D, and E before anyone considers the E 7th line, especially with several reconstruction projects planned or upcoming for the 2020-period. Maybe that timeline will shift once Riverview/Rush planning is complete, but man.

DanPatchToget
Wells Fargo Center
Posts: 1645
Joined: March 30th, 2016, 1:26 pm

Re: Arterial Transit Corridor Study ("rapid bus")

Postby DanPatchToget » December 10th, 2016, 8:55 am

There has to be a way to speed this up. I thought the original plan was opening one ABRT route every year.

Silophant
Moderator
Posts: 4470
Joined: June 20th, 2012, 4:33 pm
Location: Whimsical NE

Re: Arterial Transit Corridor Study ("rapid bus")

Postby Silophant » December 10th, 2016, 10:34 am

E Line should continue up into University where the 6U already goes. Making the final stop Stadium Village station.
Agreed. It would be nice if the E Line did its own thing in addition to being a Band-Aid for the crappy SWLRT routing.
Not sure I love the perception of Minneapolis getting SW, Bottineau, Orange, half of A and lines B, C, D, and E before anyone considers the E 7th line, especially with several reconstruction projects planned or upcoming for the 2020-period. Maybe that timeline will shift once Riverview/Rush planning is complete, but man.
To be nitpicky, the B Line extends a bit more than twice as far into St. Paul as the A Line extends into Minneapolis, but, yeah, it's pretty lopsided.
There has to be a way to speed this up. I thought the original plan was opening one ABRT route every year.